top of page
설치방법(국문)

( ​※ This image is only for understanding.)

※ Precautions before installation
· Check the main breaker status to turn off.

※ Process for installation

① Open the door of main distribution board.
 

② Turn off the main breaker and check voltage on the secondary of main breaker by meter.
 

③ Find out the proper place to put products inside the main distribution panel safely, and put it.
 

④ Loose the bolt or nut on the secondary of main breaker, and Connect the cable terminal of product on the secondary of main breaker of each phase.
 

⑤ Bind the cable by cable tie after well arrange the cable with existing cables.
 

⑥ Turn on the main the main breaker and check the all equipment are operated as normal.

Primary

Phase N

Main breaker

Secondary

설치1.png

I. Installation of FORCE
* Always consult a Licensed Electrician before working on any electric.
* In no way is this meant to be construed as instructional procedures to installing FORCE, or performing work in an Electrical panel.

Parts: 2- Y-terminal (white), 2- Plugin terminal (yellow), 2- Cable, Device (FORCE), 2- Rubber ring, 2- Cap, 4-1 inch screw (Y and Plugin terminals are attached to the cable)

· First locate your MAIN BREAKER, then TURN OFF THE MAIN BREAKER, Turn OFF All Breakers. (**Please double-check with the electrical meter to ensure the electricity is off before removing the panel cover**)

· After double-checked the electricity is OFF, then carefully remove the panel cover. Put Rubber ring (the narrow side facing Y-terminal) through Plugin terminal, then connect Plugin terminal to the Force Device until you hear "click"
 

· Put Cap through Y-terminal and bring it towards to device to close (twist), make sure Plugin terminal is connected to the Force Device fully, and seal properly with Cap.

· Mount the FORCE device anywhere within 39 inches (1 meter) from the panel.
 

· Unscrew the bolt & nut that is attached to the bus bar, then connect one Y-terminal (white) on the left side of the bus bar and screw the bolt & nut tight. Then follow procedure # 2-4 to connect another Y-terminal to the right side of the bus bar.
 

· Safely install the panel cover back.
 

· Turn on the main breaker. DONE!

( ​※ This image is only for understanding.)

설치2.png

II. Installation of FORCE

* Always consult a Licensed Electrician before working on any electric.
* In no way is this meant to be construed as instructional procedures to installing FORCE, or performing work in an Electrical panel.

Parts: 2- Y-terminal (white), 2- Plugin terminal (yellow), 2- Cable, Device (FORCE), 2- Rubber ring, 2- Cap, 4-1 inch screw (Y and Plugin terminals are attached to the cable.)

· First locate your MAIN BREAKER, then TURN OFF THE MAIN BREAKER, Turn OFF All Breakers. (**Please double-check with an electrical meter to ensure the electricity is off before removing the panel cover**)

· After double-checked the electricity is OFF, then carefully remove the panel cover.

· Put Rubber ring (the narrow side facing Y-terminal) through Plugin terminal, then connect Plugin terminal to the Force Device until you hear "click"
 

· Put Cap through Y-terminal and bring it towards to device to close (twist), make sure Plugin terminal is connected to the Force Device fully, and seal properly with Cap.

· Mount the FORCE device anywhere within 39 inches (1 meter) from the panel.
 

· Cut off Y-terminal from the cable, and peel about 12 inches from the tip of the cable cover (COVER ONLY).
 

· Connect cables to the switches.
 

· Remove the very first two switches from 1 or 2 side of the panel as shown in diagram.
 

· Connect both of the FORCE attached switches on the first two top breakers of the panel that you have selected.
 

· After installing the FORCE switches on the panel you selected, turn ON switches ONLY! (NOT A MAIN BREAKER).
 

· Safely install the panel cover back.
 

· Turn ON the MAIN BREAKER. DONE!

( ​※ This image is only for understanding.)

Q&A

We have summarized your frequent inquiries below, so please check if you have any questions.
If you have any other questions, please feel free to contact us. I'll guide you with all my heart.

Q. Will there be any problems with the main panel after installing the FORCE?
└ No, There will be no problems at all with the main panel because of Force.

Q. What should I do with FORCE, if I move to another place after installing?
└ You can easily uninstall the Force out of an existing location and re-install at a new location. For the moment only think about whether the capacity of FORCE is proper or not. Also, we don’t provide installation service at this time, so customers are responsible for uninstalling and installing.

Q. Which location should the FORCE be installed?
└ The best location to install FORCE is secondary of the main circuit breaker of the main distribution board. (For more detail, please visit our website you can find installation under SUPPORT.)

Q. Does the main panel need to be turned off during the FORCE installation?
└ Yes, For your safety, if you don't shut the main panel, you will get injured (electric shock) by electricity.

Q. How much electricity bill will be saved with the FORCE?
└ More than 5%, The saving ratio will vary depending on the circumstances, and it is hard to calculate when it comes to electricity bill cost. But average saving will be up to 5%~15%.

Q. What's the principle of energy-saving? / How does FORCE reduce power consumption?
└ The FORCE saves active power by increasing conductivity. And it reduces electrical losses by excess free electrons. (Active Power Saving by Increasing Conductivity)

Q. Is the FORCE able to install in factories or large buildings?
└ Yes, it is. The Force can be installed anywhere that uses electricity. The Force is not restricted by the installation environment.

Q. Is the rental(lease) service available?
└ Yes, see below for more detail. However, we only provide rental service in the US only for industrial, commercial and vessels. (For more detail and inquiry, please visit our website, there is Contact us under SUPPORT)

Q. Are there any cases where the FORCE does not reduce power consumption?
└ Absolutely not, only the saving ratio is different. Reduction failure has not occurred in the past 12 years, but the saving ratios are different depending on circumstances. Also, for sure there should be a reduction effect only if the FORCE is installed properly.


Q. Is there any harmonic wave or noise after installing the FORCE?

└ No, there is none. The Force doesn’t operate with electricity or on motors, so there will be no Noise, Heat or Harmonics distortion.

Q. Is the FORCE supported by the government?

└ Not at the moment. But once we have any type of support from the government we will post on the website under News, so please check our website frequently for updates.

Q. Is the after service available for the FORCE?
└ Yes, But our product is a maintenance free commodity, The Force doesn’t need maintenance. If so, please contact us.

Q. What if the FORCE device has the same issues after service?
└ Enposs cares for Customers. If there is an issue with the product after service, please contact us within 30 days after being serviced.

Q. The FORCE's power saving rate is good at the first test, but can it drop over time?

└ No, it will not.